Traffic Advisory: delays on Aspen, Noel, Bolt (Oct 16 - Nov 28, 2025)

Traffic Advisory
Date
There will be traffic delays from Oct 16 to Nov 28, 2025.

Hazelwood Construction Services Inc. will be doing a construction project for the Town in the areas shown on map below, which are:

  • Aspen Road (from Guthrie Road to Noel Avenue), 
  • Noel Avenue (to Anderton Road), 
  • Bolt Avenue (from Aspen Road to the school zone) 
The Project will result in the following:
  • Traffic disruption and Lane Shifting (temporary centre line moved) on Aspen Road & Noel Avenue, 
  • Traffic Control Persons at the Intersection (Aspen Rd & Bolt Ave) and,
  • Single Lane Alternating Traffic (Bolt Avenue). 
  • Construction signage and Traffic Control personnel and equipment will be in place during any works affecting the flow of traffic.
  • TRAFFIC DELAYS CAN BE EXPECTED – PLEASE RESPECT TRAFFIC CONTROL PERSONNEL AND GIVE YOURSELF EXTRA TIME TO GET THROUGH THE WORK AREA.
  • There will be no on-street parking on Aspen Road (from Meadowlark Dr to Bolt Ave) during this construction period and on Bolt Avenue (from Aspen Rd to the School Zone). 
  • During Line Painting works there will be no on-street parking on Aspen Road and Noel Avenue.
  • Access for emergency vehicles will be maintained at all times.

Should you have any questions, please contact Hazelwood Construction Services at phone: 250-716-1940 or email general@hazelwood.ca

Click here to view the General Construction Notice to Residents from Hazelwood Construction.